This article aims at proposing integration strategies for the photovoltaic solar power plant in a highly overloaded low voltage distribution network in order to ensure a good energy policy in the electricity distribution network of the city of Kinshasa. The application case was taken to the distribution network served by the BOSAWA booth in the MIKONDO / KIMBANSEKE district. After evaluation of the installed capacity resulting from the deficit rising to 457.82kVA; after projection of the parameters of the current network for a duration of 13 years (from 2018 to 2030) the power was estimated at 863,28kVA.
The proposed system will ensure that the energy policy of the city of Kinshasa (distribution network served by the MT / BT BOSAWA substation) can encompass the three components of the operational safety, including: reliability, availability and security in supply of electrical energy in the capital of the Democratic Republic of Congo.