The LIMINGA substation in the municipality of LIMETE, one of the three nodes of the City of KINSHASA’s HV distribution network, is experiencing operating difficulties due in particular to the absence of an optimal planning sheet, capable of concretely defining the priority areas for intervention. This substation is a key facility in the city, supplying power to the communes of LIMETE, LEMBA, MASINA, MATETE, KINSESO MAKALA, NGABA, KIMBANSEKE, N’DJILI and NGALIEMA. It is therefore of paramount interest to analyze the operating parameters of its 30/6.6 kV and 30/20 kV distribution network in this entity, in order to avoid the alarming situation of load shedding, black pockets and lack of electricity that the population of these communes is often confronted with on a daily basis.