[ Stratégies d’intégration de la production décentralisée à base d’énergie solaire photovoltaïque dans le réseau basse tension fortement surcharge: Application au réseau de distribution BT desservi par la cabine Bosawa, Kimbanseke-Kinshasa ]
Volume 39, Issue 1, March 2023, Pages 259–270
Ndumbi Kapuku Charles1 and Assani Saidi2
1 Institut supérieur de techniques appliquées, Domiongo Kasai, RD Congo
2 Institut supérieur de techniques appliquées, Domiongo Kasai, RD Congo
Original language: French
Copyright © 2023 ISSR Journals. This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
This article aims at proposing integration strategies for the photovoltaic solar power plant in a highly overloaded low voltage distribution network in order to ensure a good energy policy in the electricity distribution network of the city of Kinshasa. The application case was taken to the distribution network served by the BOSAWA booth in the MIKONDO / KIMBANSEKE district. After evaluation of the installed capacity resulting from the deficit rising to 457.82kVA; after projection of the parameters of the current network for a duration of 13 years (from 2018 to 2030) the power was estimated at 863,28kVA. The proposed system will ensure that the energy policy of the city of Kinshasa (distribution network served by the MT / BT BOSAWA substation) can encompass the three components of the operational safety, including: reliability, availability and security in supply of electrical energy in the capital of the Democratic Republic of Congo.
Author Keywords: Strategies, integration, decentralized production, solar energy, photovoltaic, low voltage network, heavily, overloaded.
Volume 39, Issue 1, March 2023, Pages 259–270
Ndumbi Kapuku Charles1 and Assani Saidi2
1 Institut supérieur de techniques appliquées, Domiongo Kasai, RD Congo
2 Institut supérieur de techniques appliquées, Domiongo Kasai, RD Congo
Original language: French
Copyright © 2023 ISSR Journals. This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Abstract
This article aims at proposing integration strategies for the photovoltaic solar power plant in a highly overloaded low voltage distribution network in order to ensure a good energy policy in the electricity distribution network of the city of Kinshasa. The application case was taken to the distribution network served by the BOSAWA booth in the MIKONDO / KIMBANSEKE district. After evaluation of the installed capacity resulting from the deficit rising to 457.82kVA; after projection of the parameters of the current network for a duration of 13 years (from 2018 to 2030) the power was estimated at 863,28kVA. The proposed system will ensure that the energy policy of the city of Kinshasa (distribution network served by the MT / BT BOSAWA substation) can encompass the three components of the operational safety, including: reliability, availability and security in supply of electrical energy in the capital of the Democratic Republic of Congo.
Author Keywords: Strategies, integration, decentralized production, solar energy, photovoltaic, low voltage network, heavily, overloaded.
Abstract: (french)
Cet article a pour objectif la proposition des stratégies d’intégration de la centrale solaire photovoltaïque dans un réseau de distribution basse tension fortement surchargé en vue d’assurer une bonne politique énergétique (influant sur la diversification des sources primaires d’énergie pour assurer un mix énergétique équilibré et adapté aux usages, aux territoires et aux impacts sur l’environnement) dans le réseau de distribution d’électricité de la ville de Kinshasa en partant du système BT. Le cas d’application était porté au réseau de distribution desservi par la cabine BOSAWA dans le Quartier MIKONDO/KIMBANSEKE. Après évaluation de la puissance installée issue du déficit se levant à 457,82kVA; après projection des paramètres de l’actuel réseau pour une durée de 13 ans (soit de 2018 à 2030) la puissance a était estimée à 863,28kVA. Le système proposé fera que la politique énergétique de la ville de Kinshasa (réseau de distribution desservi par le poste MT/BT BOSAWA) puisse englober les trois composantes de la sureté de fonctionnement, dont: la fiabilité, la disponibilité et la sécurité dans la fourniture d’énergie électrique dans la capitale de la république démocratique du Congo.
Author Keywords: Stratégies, intégration, production décentralisée, énergie solaire, photovoltaïque, réseau basse tension, fortement, surchargé.
How to Cite this Article
Ndumbi Kapuku Charles and Assani Saidi, “Strategies for integrating decentralized production based on photovoltaic solar energy into the heavily overloaded low-voltage network: Application to the LV distribution network served by the Bosawa cabin, Kimbanseke-Kinshasa,” International Journal of Innovation and Applied Studies, vol. 39, no. 1, pp. 259–270, March 2023.